1. Process Flow

2. Material Supply and Precautions

  Product ordering should select products from the original two designated certification factories. Equipment ordering should be scheduled to arrive when installation conditions are met. After equipment arrives on site, it should be stored in the on-site equipment warehouse. Invite Party A to jointly conduct an unpacking inspection. The manufacturer's technical documents should be complete, the model and specifications should meet design requirements, and accessories and spare parts should be complete. The cabinet body should have no damage or deformation, the paint should be intact without damage, and the internal electrical devices, components, and insulating porcelain parts should be complete without damage, cracks, or other defects.

3. Pre-Installation Preparation

Before installation, first verify whether the following civil works have been completed:

(1) Whether the roof and floor slabs have been constructed, and whether there is any leakage in the roof and floor;

(2) Whether the interior decoration works of the power distribution room and equipment room have been fully completed;

(3) Whether all types of embedded parts have been installed and meet the equipment installation conditions;

(4) Whether the doors and windows of the rooms have been installed;

(5) Whether all other processes that cannot be carried out after equipment installation begins have been completed.

  When installing high and low voltage cabinets, use a forklift to transport them along the basement level 1 car ramp to the nearest distance of the power transformation and distribution room, then use manual chain blocks for relocation. Power cabinets can be moved by manual labor. During transportation, they must be firmly fixed to prevent uneven force, cabinet deformation, or damage to components.

5. Fabrication and Installation of Foundation Steel

According to the drawings, the cabinets are arranged in rows and installed on foundation steel. The power distribution room uses No. 10 channel steel. During fabrication, first straighten and level the bent channel steel, then prefabricate and process the foundation steel according to the drawings, and perform rust removal. After the foundation steel is fabricated, embed it in coordination with the civil works according to the positions indicated in the drawings.

When installing the foundation channel steel, use a spirit level to level and align it. The unevenness and levelness of the foundation channel steel installation should be less than 1mm per meter and less than 5mm for the total length.

The embedded foundation channel steel of the distribution cabinets should be well grounded. According to design requirements, the grounding flat steel should be welded to the grounding grid at both ends, with the welding surface being twice the width of the flat steel.

When installing the cabinet body on the channel steel, use 0.5mm iron sheets for adjustment between the cabinet and the channel steel during alignment, but each location should not have more than 3 shims. After leveling and aligning, the panel surfaces should be consistent and arranged neatly. The cabinets and the side baffles should be tightened with bolts, and the gap at the joints between cabinets should be less than 2mm    

The grounding of the cabinets should be firm and good. Each cabinet should be separately connected to the foundation steel for grounding. Weld a nose on the side of the foundation steel at the lower left rear of each cabinet, and connect it firmly to the grounding terminal on the cabinet with a copper conductor of not less than 6mm2.

The cabinets are connected by busbars. The busbar straightening, cutting, processing, installation, painting, and oil brushing should all comply with specification requirements.

After the distribution cabinets are in place, they should be fixed by bolts pressed against the foundation channel steel, and direct welding is strictly prohibited. When the distribution cabinets are arranged individually or in rows, the verticality, levelness deviation, panel surface deviation, and overall deviation of the gaps between cabinets should meet the requirements in the following table:

No.  Item       Allowable Deviation (mm)

1 Verticality (per meter) <1.5

2 Levelness Adjacent two panel tops <2

  Row panel tops <5

3 Panel surface deviation Adjacent two panel edges <1

  Row panel surfaces <5

4 Panel joints <2

In this project, all distribution cabinets are equipped with separate working neutral busbars (N) and protective neutral busbars (PE) to connect the working neutral wire and protective neutral wire respectively. The doors of the distribution cabinets, regardless of whether they have electrical components, should be connected to the PE busbar inside the cabinet with yellow-green two-color flexible wires.

6. Precautions

Before cabinet installation, pay attention to checking the following points to ensure usage requirements:

(1) The drawers should push and pull flexibly and lightly, without jamming or collision, and drawers of the same specification should be able to interchange flexibly.

(2) The mechanical interlock and electrical interlock devices of the drawers should operate correctly and reliably, and the disconnecting switch can only be separated after the circuit breaker is opened.

(3) The center lines of the moving contacts and static contacts should be consistent, and the contacts should be in close contact to ensure that large currents passing through the contacts do not overheat. At the same time, the secondary circuit connection plugs between the drawer and the cabinet body should also maintain good contact.

(4) The contact between the drawer and the cabinet body and between the cabinet body and the frame should be good, and the grounding contacts between the drawer and the cabinet body should be tight. When the drawer is pushed in, the grounding contacts should close before the main contacts, and the opposite when pulled out.

The ordering and installation of low-voltage distribution cabinets should comprehensively consider the connection with external equipment, such as connection with enclosed busways and cable trays. The phase sequence of the reserved connection copper bars in the cabinet should match the busway, and the phase spacing should be consistent. The sealing treatment between the cable entering the cabinet and the cabinet body should use tower-type rubber sealing rings, and the cable should be firmly fixed before entering the cabinet to prevent damage to the copper bars and electrical accessories inside the cabinet due to gravity.

During the installation of busbar electrical appliances in the cabinet, the electrical clearance between bare live parts of different phases and between bare live parts and non-insulated metal frames should not be less than 20mm. If this requirement cannot be met, insulation protection measures must be taken.

7. Testing and Adjustment:

(1) Test contents: high-voltage cabinet frame, busbars, lightning arresters, high-voltage porcelain insulators, voltage transformers, current transformers, high-voltage circuit breakers, etc.

(2) Adjustment contents: adjustment of overcurrent relays, time relays, signal relays, and mechanical interlock adjustment.

(3) Insulation measurement: use a 500V megger to test the resistance of each circuit at the terminal board, and the value must be greater than 0.5 megohms.

(4) If the secondary circuit has transistors, integrated circuits, or electronic components, the inspection of that part should not use a megger, but a multimeter.

(5) Connect temporary control power and operating power, and simulate test control, interlock, operation, relay protection, and signal actions respectively.

8. Power Transmission Operation and Acceptance

(1) Close the switch of the high-voltage incoming cabinet and check whether the voltage on the voltage transformer cabinet is normal.

(2) Close the switch of the transformer cabinet and check whether the transformer is energized.

(3) Close the switch of the low-voltage incoming cabinet and check whether the three-phase voltage on the voltmeter is normal.

(4) After 24 hours of no-load operation without abnormalities, the acceptance procedures can be processed.